What is the name given to a budget which has been prepared by building on a previous period’s budgeted or actual figures?

A. Incremental budget
B. Flexible budget
C. Zero based budget
D. Functional budget

Reveal answer
Marking guide
Related textbook topics: Types of Budgetary Systems