MC Question 10

S Company is a manufacturer of multiple products and uses target costing. It has been noted that Product P currently has a target cost gap and the company wishes to close this gap.

Which of the following may be used to close the target cost gap for product P?

A. Use overtime to complete work ahead of schedule
B. Substitute current raw materials with cheaper versions
C. Raise the selling price of P
D. Negotiate cheaper rent for S Company’s premises