Specimen
2399 others answered this question

MC Question 13

A company manufactures a product which requires four hours per unit of machine time. Machine time is a bottleneck resource as there are only ten machines which are available for 12 hours per day, five days per week. The product has a selling price of $130 per unit, direct material costs of $50 per unit, labour costs of $40 per unit and factory overhead costs of $20 per unit. These costs are based on weekly production and sales of 150 units.

What is the throughput accounting ratio?

A. 1·33
B. 2·00
C. 0·75
D. 0·31