Specimen
2011 others answered this question

MC Question 8

A company has the following production planned for the next four weeks. The figures reflect the full capacity level of operations. Planned output is equal to the maximum demand per product.
Product A
$ per unit
B
$ per unit
C
$ per unit
D
$ per unit
Selling price 160 214 100 140
Raw material cost 24 56 2240
Direct labour cost 66 88 33 22
Variable overhead cost 24 18 24 18
Fixed overhead cost 16 10 8 12
Profit
30

42

13

48
Planned output 300 125 240 400
Direct labour hours per unit 6 8 3 2

It has now been identified that labour hours available in the next four weeks will be limited to 4,000 hours.

In what order should the products be manufactured, assuming that the company wants to maximise profits in the next four weeks?

A. D, A, C, B
B. D, B, A, C
C. B, A, D, C
D. D, C, A, B