Specimen
2328 others answered this question

MC Question 27

The Hi Life Co (HL Co) makes sofas. It has recently received a request from a customer to provide a one-off order of sofas, in excess of normal budgeted production. The order would need to be completed within two weeks. The following cost estimate has already been prepared:
$
Direct materials:
Fabric 200 m2 at $17 per m2 3,400
Wood 50 m2 at $8·20 per m2 410
Direct labour:
Skilled 200 hours at $16 per hour 3,200
Semi-skilled 300 hours at $12 per hour 3,600
Factory overheads 500 hours at $3 per hour 1,500
Total production cost 12,110
General fixed overheads as 10% of total production cost 1,211
Total cost
13,321
A quotation now needs to be prepared on a relevant cost basis so that HL Co can offer as competitive a price as possible for the order.

The skilled labour force is employed under permanent contracts of employment under which they must be paid for 40 hours per week’s labour, even if their time is idle due to absence of orders. Their rate of pay is $16 per hour, although any overtime is paid at time and a half. In the next two weeks, there is spare capacity of 150 labour hours.

There is no spare capacity for semi-skilled workers. They are currently paid $12 per hour or time and a half for overtime. However, a local agency can provide additional semi-skilled workers for $14 per hour.

What cost should be included in the quotation for skilled labour and semi-skilled labour?

Skilled Semi-skilled
A. $3,600 $4,200
B. $1,200 $4,200
C. $3,600 $5,400
D. $1,200 $5,400

We use cookies to help make our website better. We'll assume you're OK with this if you continue. You can change your Cookie Settings any time.

Cookie SettingsAccept