Specimen
2518 others answered this question

MC Question 26

The Hi Life Co (HL Co) makes sofas. It has recently received a request from a customer to provide a one-off order of sofas, in excess of normal budgeted production. The order would need to be completed within two weeks. The following cost estimate has already been prepared:
$
Direct materials:
Fabric 200 m2 at $17 per m2 3,400
Wood 50 m2 at $8·20 per m2 410
Direct labour:
Skilled 200 hours at $16 per hour 3,200
Semi-skilled 300 hours at $12 per hour 3,600
Factory overheads 500 hours at $3 per hour 1,500
Total production cost 12,110
General fixed overheads as 10% of total production cost 1,211
Total cost
13,321
A quotation now needs to be prepared on a relevant cost basis so that HL Co can offer as competitive a price as possible for the order.

The fabric is regularly used by HL Co. There are currently 300 m2 in inventory, which cost $17 per m2. The current purchase price of the fabric is $17·50 per m2.

The wood is regularly used by HL Co and usually costs $8·20 per m2. However, the company’s current supplier’s earliest delivery time for the wood is in three weeks’ time. An alternative supplier could deliver immediately but they would charge $8·50 per m2. HL Co already has 500 m2 in inventory but 480 m2 of this is needed to complete other existing orders in the next two weeks. The remaining 20 m2 is not going to be needed until four weeks’ time.

What is the cost of the fabric and the wood which should be included in the quotation?

Fabric Wood
A. $3,500 $419
B. $3,400 $419
C. $3,500 $255
D. $0 $255

We use cookies to help make our website better. We'll assume you're OK with this if you continue. You can change your Cookie Settings any time.

Cookie SettingsAccept