Question 3b
Introduction
Cofold Construction Co (CC) is a listed construction company. Its head office is in the capital city, Lambdahasa, of the country of Omegland. Omegland has two neighbouring countries, Alphia and Betal. The countryside in both Alphia and Omegland is generally flat. In Betal, there is a large range of mountains (the Isnardi mountains) which separates its Eastern region from the rest of the country. All three countries use the same currency, the dollar ($).
The board of CC comprises 50% executive directors and 50% independent non-executive directors. The senior board members are:
Chairman Imena Bhudia
Chief executive Burton Vadher
Senior non-executive director Alex Larsen
CC’s core business is to provide support services, such as upgrade of electricity networks and road renewal and maintenance, in all three countries. However, it has also undertaken road construction projects of increasing size and complexity. Initially, CC carried out most of its major construction projects in Omegland, its biggest project there being a ring road around the city of Lambdahasa. CC has also started to develop a portfolio in Alphia, the biggest development there being a road between Phi City and Tautown, which was completed in 20X0.
To date, CC has not carried out any road construction projects in Betal. However, an opportunity has arisen for CC to tender for construction of a major road in Betal, which would be the biggest project which CC has undertaken to date.
The following exhibits provide information relevant to CC:
Exhibit 1: Extracts from the most recent annual report of CC.
Exhibit 2: Press release of the announcement of the new road in Betal.
Exhibit 3: Forecast revenues and costs for the construction of the new road in Betal.
Exhibit 4: Outline contents of the project initiation document (PID) and a summary of the operational issues section of the PID.
Exhibit 5: Transcript of an emergency meeting at CC’s head office.
Exhibit 6: Report of an interview with Burton Vadher in Omegland Daily News newspaper.
Question 3b:
It is now July 20X2, three months after CC began construction of the new road in Betal.
You are Pat Singh, a consultant employed by CC’s board.
You have just left the emergency meeting regarding the incident at the construction site and are responding to the requests made by CC’s chairman, Imena Bhudia, at the end of the meeting.
Required:
Prepare:
(b) A summary for CC’s board to review assessing the control weaknesses discussed at the emergency meeting, stating for each control weakness its consequence and recommendation for improvements. (14 marks)
Professional skills marks are available for demonstrating evaluation skills by basing explanations of significant control weaknesses on the information provided and recommending appropriate improvements. (4 marks)