CIMA P2 Syllabus D. Risk and Control - Value at Risk - Notes 12 / 13
Value at Risk is the amount potentially lost, at a given "confidence level"
VaR is measured by using normal distribution theory.
Confidence levels are often set at either:
95% (The VaR here shows the potential loss that has only a 5% chance of decline) or
99% (The VaR considers a 1% chance of loss of value).
Illustration
Cow plc estimates the expected NPV of a project to be £100 million, with a standard deviation of £9.7 million.
Required:
Establish the value at risk using both a 95% and also a 99% confidence level.
Solution
Using Z = (X - μ) / σ
where
X = result we are considering
μ = mean
σ = standard deviationEstablishing Z from the normal distribution tables
ie at a 95% (0.95) confidence level, 1.65 is the value for a one tailed 5% probability of decline (i.e. 0.95 - 0.50 = 0.45 = 0.4505 from the normal distribution table)
and at a 99% (0.99) confidence level, 2.33 is the value for a one tailed 1% probability of loss of NPV (i.e. 0.99 - 0.50 = 0.49 = 0.4901 from the normal distribution table).
At 95% confidence level, Z = (X-100) / 9.7 = –1.65;
therefore X = (9.7x–1.65)+100 = 84
At 99% confidence level, Z = (X-100) / 9.7 = –2.33;
therefore X = (9.7x–2.33)+100 = 77.4
There is a 5% chance of the expected NPV falling to £84 million or less and a 1% probability of it falling to £77.4 million or below.

Value at risk can be quantified for a project using simulation to calculate the project’s standard deviation.
In this context, the standard deviation needs to be adjusted by multiplying by the square root of the time period ie
95% value at risk = 1.645 x standard deviation of project x √time period of the project
Illustration
A four-year project has an NPV of $2m and a standard deviation of $1m per annum.
Required
Analyse the project’s value at risk at a 95% confidence level.
The VAR at 95% is 1.645 x 1,000,000 x √4 = $3,290,000
ie worst case NPV (only 5% chance of being worse) = $2m – $3.29m = – $1.29m
Illustration
A simulation has been used to calculate the expected value of a project and is deemed to be normally distributed with the following results:
Mean = $40,000 (positive)
Standard deviation = $21,000
Calculate the following:
a) The probability that the NPV of the project will be greater than 0.
b) The probability that the NPV will be greater than $45,000.
a)
Using Z = (X - μ) / σ
μ = $40,000
σ = $21,000
X = 0Z = (0 - 40,000) / 21,000
Z = 1.90From normal distribution table
1.90 = 0.4713 + 0.50 = 0.9713 = 97% probability that NPV >0
b)
Using Z = (X - μ) / σ
Z = (45,000 - 40,000) / 21,000
Z = 0.24From normal distribution table
0.24 = 0.0948
then
0.50 - 0.0948 = 0.4052 = 41% probability that the project's NPV > $45,000