CIMA P2 Syllabus B. Capital Investment Decision Making - Adjusted Payback - Notes 2 / 11
This incorporates risk into the payback method we looked at earlier in the course
2 Methods
Add payback to NPV - Only projects with +ve NPV and payback within specified time chosen
Discount cashflows used in payback with a risk adjusted discount rate
Illustration of method 2
Year | Cashflow |
0 | (1,700) |
1 | 500 |
2 | 500 |
3 | 600 |
4 | 900 |
5 | 500 |
Calculate discounted payback at a rate of 12%
Solution
Year | Cashflow | 12% | Cashflow | Cumulative |
0 | (1,700) | 1 | (1,700) | (1,700) |
1 | 500 | 0.893 | 446.5 | (1,253) |
2 | 500 | 0.797 | 398.5 | (855) |
3 | 600 | 0.712 | 427.2 | (427.8) |
4 | 900 | 0.636 | 572.4 | 144.6 |
5 | 500 | 0.567 | 283.5 | 428.1 |
Discounted payback = 3 years 9 months
NPV = 428,100
Risk Adjusted Discount Rates
The discount rate should reflect:
Cost of debt
Cost of equity
The mix of the 2 above adjusted for riskiness
If a project gives additional risks then the discount factor should be altered accordingly. This is called the risk premium
Previous
Payback method
Syllabus B. Capital Investment Decision Making
Investment Appraisal Techniques
Next up
Accounting Rate of Return
Syllabus B. Capital Investment Decision Making
Investment Appraisal Techniques