Determining the Optimal Production Plan re a single limiting factor 2 / 5

Planning with one limiting factor

When there is only one scarce resource, key factor analysis can be used to solve the problem.

Options must be ranked using contribution earned per unit of the scarce resource.

Three steps in key factor analysis

  1. Step 1: - First determine the limiting factor (bottleneck resource)

  2. Step 2: - Rank the options using the contribution earned per unit of the scarce    resource

  3. Step 3: - Allocate resources

Product AProduct B
SP / Unit100120
VC / Unit8075
FC / Unit1012
Skilled Labour / Unit0.5 hr0.75 hr
Demand (units)5,0004,000
How many labour hours are required?
Required: Product A (0.5 x 5000)2,500
Required Product B (0.75 x 4000)3,000
5,500
Available4,000
Shortfall1,500
Labour hours are a limiting factor

Product AProduct B
SP / Unit100120
VC / Unit8075
Cont / Unit2045
Lab hrs / Unit0.50.75
Cont / Lab hr4060
Ranking21
Prod Plan
ProductUnitsLab Hrs / UnitTotal Lab Hrs
Available = 4,000
Product B4,0000.75 (3,000)
Available 1,000
Product A1,000/0.5 = 2,0000.5 (1,000)
Available 0

Therefore, produce 2000 units of Product A and 4000 units of Product B

Assumptions

  1. A single quantifiable objective.  In reality, there may be multiple objectives.

  2. Each product always uses the same quantity of the scarce resource per unit.

  3. The contribution per unit is constant. However, the selling price may have to be lowered to sell more; discounts may be available as the quantity of materials needed increases.

  4. Products are independent. It may not be possible to prioritise product A at the expense of product B.

  5. We focus on the short term, therefore ignoring fixed costs.

We use cookies to help make our website better. We'll assume you're OK with this if you continue. You can change your Cookie Settings any time.

Cookie SettingsAccept