Project Plan Steps

NotesQuizObjective Test

The steps are:

  1. Divide the project into work packages - This is done using the work breakdown structure. It clearly identifies the person responsible for each activity or work package. Those responsible for each work package are asked to estimate the time and resources needed for their work package and the tasks and activities that comprise it.

  2. Estimate resources and costs

  3. Define the activities graphically

  4. Determine the project schedule and budget - This involves producing a baseline budget that presents a realistic assessment of the time and funding required, and the available resources to complete the project objective.

Project management plan

A project management plan would be issued to stakeholders such as corporate management, the contracting company, customers and the project team. There are no set layouts of project management plans.