CIMA E2 Syllabus C. Managing projects - PERT - Formula - Notes 13 / 16
PERT uses a formula to calculate an expected time for each activity.
It uses 3 time estimates for each activity.
using a formula to calculate an expected time for each activity.
An optimistic estimate denoted by 'o'.
A probable estimate denoted by 'm'.
A pessimistic estimate denoted by 'p'.
The formula to calculate average completion time using PERT is (o + 4m + p)/6